GAO: Questionable Fees Paid on FBI Trilogy Project

Alice Lipowicz writes on GCN.com:

The FBI paid at least $10.1 million in questionable contractor costs related to its controversial Trilogy IT modernization program, according to a new report from the Government Accountability Office.

For example, in a single invoice for March 2002 from contractor DynCorp, which is now part of Computer Sciences Corp., the FBI was billed $1.9 million for “other direct costs” with no explanation.

“No additional information was provided on the invoice to explain what made up these costs,” the GAO report said.

More here.